Project Name |
|
|
Surface Transportation Program Cost Overruns (Grouping) |
|
TIP # |
|
2008-89-005 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Improvement Type |
Contingency Funding |
|
Lead Agency |
|
TDOT |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
County |
|
|
Multi-County |
|
Length |
|
0.00 |
|
Regional Plan ID |
Consistent |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Air Quality Status |
Exempt |
|
TDOT PIN |
|
|
|
Project Cost |
|
$7,900,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Route |
|
STP Project Cost Overruns (Project Grouping) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location |
|
Regionwide - Nashville Area MPO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Description |
|
Surface Transportation Program funds to cover overruns on project phases which were included in previous State Transportation Improvement Programs (STIPs). |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year |
Type of Work |
Funding Type |
Total Funds |
Federal Funds |
State Funds |
Local funds |
|
2011 |
PE-D, ROW, CONSTRUCTION |
STP |
$2,900,000.00 |
$2,320,000.00 |
$580,000.00 |
$0.00 |
|
2012 |
PE-D, ROW, CONSTRUCTION |
STP |
$2,500,000.00 |
$2,000,000.00 |
$500,000.00 |
$0.00 |
|
2013 |
PE-D, ROW, CONSTRUCTION |
STP |
$2,000,000.00 |
$1,600,000.00 |
$400,000.00 |
$0.00 |
|
2014 |
PE-D, ROW, CONSTRUCTION |
STP |
$500,000.00 |
$400,000.00 |
$100,000.00 |
$0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVISION HISTORY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
8/12/2011 |
Amend# 2011-029 |
Project adjusted to add $1,920,000 (federal) to FY 2011. |
|
|
|
|
|
12/27/2011 |
Amend# 2011-037 |
The modification adds $1,600,000 (federal) to FY 2012 |
|
|
|
|
|
2/19/2013 |
Amend# 2013-013 |
Project modified to add $1,200,000 (federal share) in STP funds to fiscal year 2013. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT NOTES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
STP Project Cost Overruns (Project Grouping) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nashville Area Metropolitan Planning Organization |
|
|
Transportation Improvement Program for FYs 2011-2015 |
|
Printed on |
Sunday, May 11, 2025 |
|
|
|
|
|
|
|
|
Page |
1/1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|