Transportation Improvement Program for FYs 2011-2015
Project Name Long Hollow Pike Traffic Signal
Synchronization
TIP # 2011-57-024
Improvement Type ITS Lead Agency Goodlettsville
County Sumner County Length 0.00 Regional Plan ID 1017-267
Air Quality Status Exempt TDOT PIN Project Cost $300,000.00
Route Long Hollow Pike Traffic Signal Synchronization
Location Beginning on South Main Street at Memorial Drive north to Long Hollow Pike then east along Long Hollow
Pike to Loretta Drive.
Project Description Install a coordinated (fiber optic) traffic signal system for several Long Hollow Pike intersections. Cameras
will be installed at each intersection and existing incandescent signal heads will be converted to LED.
Fiscal Year Type of Work Funding Type Total Funds Federal Funds State Funds Local funds
2012 PE-N CMAQ $7,700.00 $7,700.00 $0.00 $0.00
2012 PE-D CMAQ $42,270.00 $42,270.00 $0.00 $0.00
2012 CONSTRUCTION CMAQ $250,030.00 $250,030.00 $0.00 $0.00
REVISION HISTORY
12/28/2011 Amend# 2011-038 This modification updates
the FY and amounts for the
PE NEPA, PE Final Design
and Construction phases.
The total project cost
remained the same.
5/31/2013 Amend# 2013-030 Project modified to shift
funds between phases to
reflect update cost estimates
including CEI costs.  The
total project cost remains the
same.