Project Name |
|
|
Cedar City Trail - Phase 5 (Bartons Creek South) |
|
TIP # |
|
2011-76-035 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Improvement Type |
Greenway |
|
Lead Agency |
|
Lebanon |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
County |
|
|
Wilson County |
|
Length |
|
2.00 |
|
Regional Plan ID |
1076-305 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Air Quality Status |
Exempt |
|
TDOT PIN |
|
|
|
Project Cost |
|
$1,438,437.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Route |
|
Cedar City Trail - Phase 5 (Bartons Creek South) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location |
|
From East of Hartmann Drive along Bartons Creek |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Description |
|
Multi-use paved trail extension from trailhead location at Hickory Ridge Road along Bartons Creek to the south connecting with existing and proposed schools and continues towards Leeville Pike and across Bartons Creek to the new Winfree Bryant Middle School. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year |
Type of Work |
Funding Type |
Total Funds |
Federal Funds |
State Funds |
Local funds |
|
2013 |
PE-N |
CMAQ |
$11,000.00 |
$8,800.00 |
$0.00 |
$2,200.00 |
|
2013 |
ROW |
CMAQ |
$25,000.00 |
$20,000.00 |
$0.00 |
$5,000.00 |
|
2013 |
PE-D |
CMAQ |
$99,000.00 |
$79,200.00 |
$0.00 |
$19,800.00 |
|
2014 |
CONSTRUCTION |
CMAQ |
$24,500.00 |
$19,600.00 |
$0.00 |
$4,900.00 |
|
2014 |
CONSTRUCTION |
ENH |
$1,278,937.00 |
$1,023,150.00 |
$0.00 |
$255,787.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVISION HISTORY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
7/11/2011 |
Amend# 2011-014 |
Include Phase 6 which has
received Enhancement funds
and is being combined with
Phase 5 already in the TIP.
The City of Lebanon is using
PE and the donation of ROW
as soft match for the project.
shares for the project remain
an 80/20 split. Construction
Engineering Inspection (CEI)
Construction phase funds.
|
|
|
|
|
|
4/18/2013 |
Amend# 2013-021 |
This is a project in the current TIP. The amendment adds remaining funds from previous phases 3 and 4 of the same project to Phase 5. Also, the project description has been revised to properly describe the alignment. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT NOTES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|