NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Transportation Improvement Program for FYs 2014-2017 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name |
|
|
Increased Guidance for Improved Mobility |
|
TIP # |
|
2004-004 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Improvement Type |
Signage/Wayfinding |
|
Lead Agency |
|
Metro Nashville |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
County |
|
|
Davidson County |
|
Length |
|
0.00 |
|
Regional Plan ID |
1017-193 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Air Quality Status |
Exempt |
|
TDOT PIN |
|
103489.00 |
|
Project Cost |
|
$600,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Route |
|
Increased Guidance for Improved Mobility |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Location |
|
High volume corridors (e.g. West End), tourist areas, major intersections |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Description |
|
Provide street names signs, guidance signs, pedestrian signalization to improve way finding for motorists & pedestrians. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fiscal Year |
Type of Work |
Funding Type |
Total Funds |
Federal Funds |
State Funds |
Local funds |
|
2014 |
CONSTRUCTION |
U-STP |
$450,000.00 |
$360,000.00 |
$0.00 |
$90,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
REVISION HISTORY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PROJECT NOTES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Engineering on this project has been completed. Pedestrian oriented wayfinding maps and directional signage has been installed in the Downtown and West End neighborhoods. The remaining construction funds will be used to install internally illuminated street name signs at high volume intersections. The project should take 12 months to complete from notice toproceed. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nashville Area Metropolitan Planning Organization |
|
|
Transportation Improvement Program for FYs 2014-2017 |
|
Printed on |
Saturday, December 21, 2024 |
|
|
|
|
|
|
|
|
Page |
1/1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|