12/18/12 -Phase 1:Design Completed in 2010. Currently in
Right of Way Stage - updated appraisal and review appraisal
completed in April 2011, negotiations began with property
owner in May 2011. Negotiation with property owner
continues.Construction funding for Phase 1 is included in this
TIP request. The construction of the Phase 1 greenway trail is
anticipated to last 150 days.Phase 2:Design Completed in
2011. Right of Way Stage Complete and approved by TDOT
Advertised for Bids in August 2011 - Notice to Proceed to
Contractor for Construction in December 2011.Construction
completion in July 2012Phase 2 Grand Opening Event held in
October 2012.Phase 3:Phase 3AEngineering Design
Completion December 2011. Submittal of Design Plans to
funding agency January 2012. Active Transportation Grant
Announcement January 2012. Advertised for Bids in October
2012 - Notice of Award given to Contractor in November
2012.Construction Completion is anticipated to be May 2013.
Phase 3BPhase 3B Engineering Design will begin in January
2013 with design completion in April 2013.Construction
funding for Phase 3B is included in this TIP request. The
construction of the Phase 3B greenway trail and pedestrian
bridge is anticipated to last 180 days.The County will utilize
Wiser Company for the Phase 3B design. Wiser Company has
completed all of the design for the Lower Station Camp
Greenway phases. Phase 3B design should be completed in
April 2013. The TIP funding will be utilized for construction and
construction engineering inspection fees.Once design is
complete in April and construction funds are obtained, Phase
3B will be ready to proceed to construction. Phase 1 design
has been completed; Phase 1 will be ready to proceed to
construction once the right of way is obtained. The Lower
Station Camp Greenway is a priority project for Sumner