NASHVILLE AREA METROPOLITAN PLANNING ORGANIZATION
Transportation Improvement Program for FYs 2014-2017
Project Name Sanders Ferry/ Drakes Creek Bike Trail TIP # 2012-56-171
Improvement Type Greenway Lead Agency Hendersonville
County Sumner County Length 1.52 Regional Plan ID Consistent
Air Quality Status Exempt TDOT PIN 117016.00 Project Cost $2,438,000.00
Route Sanders Ferry/ Drakes Creek
Location From Main Street along Sanders Ferry Rd and Drakes Creek/Old Hickory Lake to Sanders Ferry Park
Project Description Construct 8-ft wide bike/ped trail and boardwalk along Sanders Ferry Rd along the water’s edge of Drakes
Creek/Old Hickory Lake.
Fiscal Year Type of Work Funding Type Total Funds Federal Funds State Funds Local funds
2016 PE-D CMAQ $79,300.00 $63,440.00 $0.00 $15,860.00
2016 CONSTRUCTION CMAQ $1,288,700.00 $1,030,960.00 $0.00 $257,740.00
2016 PE-N U-STP $74,600.00 $59,680.00 $0.00 $14,920.00
2016 CONSTRUCTION U-STP $875,400.00 $700,320.00 $0.00 $175,080.00
REVISION HISTORY
12/17/2015 Amend# 2016-008 This project was adjusted to
add $760,000 (federal) in
FY16 U-STP funds from
TIP# 2002-028 for PE-N and
CONST. Additionally,
$40,000 (federal) in FY14
CMAQ funds originally to be
used for ROW were shifted
to FY16 PE-D and CONST.
PROJECT NOTES
12/17/12 - Schedule:  Oct, 2013 - Receive Notice To Proceed
from TDOT to acquire ROW.Nov, 2013-Mar, 2014 - Acquire
ROW and easements; adjust utilities if needed.Apr, 2014 -
Receive Notice To Proceed from TDOT to advertise for
construction.May, 2014 - Award contract for construction.May,
2014-Dec 2014 - Complete construction and closeout.The
project will be managed by the City’s Public Works Department
and Engineering Consultant.  All contracts (engineering, ROW
acquisition and construction) will include schedules with
milestones and dates.  One of the main criteria in choosing the
engineering consultant will be performance and proven
knowledge of TDOT requirements and track record in working
with TDOT.The City has successfully managed the following
projects:1. Indian Lake Boulevard at 386 Bridge widening,
ramps, signals.2. New Shackle Island Road3. Traffic Signal
Upgrade4. ARRA ProjectsWhile the City experienced some
difficulty in getting through the TDOT process, once a Notice
To Proceed with construction was received, the projects were
completed on time and within budget.
Nashville Area Metropolitan Planning Organization Transportation Improvement Program for FYs 2014-2017