TIP Project #2002-028: Rockland Road Widening

Widen Rockland Rd from 2 lanes to 3 lanes along the existing alignment from W. Main St to Imperial Blvd. This project will include drainage, curb and gutter, a multi-use path and landscaping.

M Road Widening Regional Plan ID: 1052-177
Hendersonville TDOT PIN: 043162.00
Sumner County Total Cost: $12,624,690.00
Rockland Road Total Programmed: $933,500.00
West Main St. to Imperial Blvd. Federal Share: $746,800.00
1.50 miles Federal Obligation*:
Non-Exempt Unobligated Balance: $746,800.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2017PE-DU-STBG$200,000.00$160,000.00$0.00$40,000.00
2018ROWU-STBG$733,500.00$586,800.00$0.00$146,700.00
TOTAL  $933,500.00$746,800.00$0.00$186,700.00

Construction Reserve Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2019CONSTRUCTIONU-RSV$3,750,000.00$3,000,000.00$0.00$750,000.00
TOTAL  $3,750,000.00$3,000,000.00$0.00$750,000.00

Obligated Funds

There is no obligated funding information for this TIP Project.

Project Images and Videos

2002-028

Project Documents and Links

Project Notes

NotePosted On
12/17/12 - Schedule:
Oct 2014 - New/amended contract with TDOT.
Nov 2014 - Receive Notice To Proceed from TDOT for PE.
Dec 2014-Sept 2015 - PE NEPA and Design.
Oct 2015 - Notice To Proceed from TDOT for ROW and Utilities.
Nov 2015-Sept 2016 - Acquire ROW; adjust utilities.
Oct 2016-Sept 2017 - Construction and closeout.

The project will be managed by the City’s Public Works Department and Engineering Consultant. All contracts (engineering, ROW acquisition and construction) will include schedules with milestones and dates. One of the main criteria in choosing the engineering consultant will be performance and proven knowledge of TDOT requirements and track record in working with TDOT
12/17/2012

Project Amendments

There are no amendments for this TIP Project.

Administrative Modifications

There are no administrative modifications for this TIP Project.

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*  
Phone #:  
Email address:  

Your comment:

Please limit your comment to 2,000 characters.