12/17/12 Schedule: Oct, 2013 - Receive Notice To Proceed from TDOT for Construction. Nov, 2013-Dec, 2013 - Advertise for Construction Bids and CEI. Jan, 2014-Feb, 2014 - Award Construction and CEI Contracts. Mar, 2014-Feb, 2015 - Complete Construction and closeout.
The project will be managed by the City’s Public Works Department and Engineering Consultant. The construction contract and the CEI contract will include schedules with milestones and dates. One of the main criteria in choosing the engineering consultant will be performance and proven knowledge of TDOT requirements and track record in working with TDOT. | 12/17/2012 |