TIP Project #2008-64-037: SR-106 (Hillsboro Rd ) and SR-46 Re-alignment/ Signalization.

Realign intersection to create a 90 degree alignment, with turn lanes of appropriate stacking length on both roadways. Relocate existing signal.

M Intersection Regional Plan ID: 1064-252
Williamson County TDOT PIN: 107914.00
Williamson County Total Cost: $2,457,250.00
SR-106 (Hillsboro Rd)/ SR-46 Total Programmed: $2,457,250.00
SR-46 (Old Hillsboro Rd)/ SR-46 Federal Share: $1,965,800.00
0.10 miles Federal Obligation*:
Exempt Unobligated Balance: $1,965,800.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2017PE-DU-STBG$104,250.00$83,400.00$20,850.00$0.00
2017ROWU-STBG$35,000.00$28,000.00$7,000.00$0.00
2018ROW, CONSTRUCTIONU-STBG$2,318,000.00$1,854,400.00$463,600.00$0.00
TOTAL  $2,457,250.00$1,965,800.00$491,450.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

There is no obligated funding information for this TIP Project.

Project Images and Videos

Project Notes

NotePosted On
12/18/12-
Once the engineering phase is complete (see 2011-2014 TIP), a truer picture of the project scope will be known. However, based on the above noted TPR, a new alignment for SR-46 is to be constructed to provide a skew of 90 degrees. This alignment is to be located in the ROW previously acquired by Williamson County. This new section of roadway would include two 12' left and right turn lanes in addition to 6' paved shoulder. On SR-1 06, a new 12' left tum lane is to be constructed, as well as a
new 12' right tum lane (south approach). It is intended that intersection signalization be actuated with two phase operation due to the relatively low volumes on SR-46.
Major Tasks/Activities- assuming completion of the engineering phase in FY-13, ROW phase should begin in FY14, and construction in FY-15.
Schedule- assuming completion of the engineering phase previous funded in FY 2011-14
TIP in FY-13, ROW acquisition (if necessary) would commence in FY-14, and actual
construction in FY -15.
• Milestones, et al- Williamson County Government has successfully managed a number of similar projects, including signalization at SR-106 and Murray Lane, SR-1 06 and Sneed Road (including left tum lane), SR 106 and Berrys Chapel Road, SR 106 and Battlewood Court, SR46 and SR-96, and SR-106 and Manley Lane. These projects were developed and implemented from 1994 through 2009.
12/18/2012

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2018-022This amendment proposes to program construction funds in the amount of $1,854,400 (federal) FY 2018 U-STBG funds. ROW will also be an eligible type of work for the added funding.6/20/2018  

Administrative Modifications

There are no administrative modifications for this TIP Project.

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.