TIP Project #2020-14-103: I-24 Ramp Improvements at Exit 59

This project involves the improvement of ramps at the I-24 and Bell Road (SR-254) interchange (Exit 59).

M Safety Regional Plan ID: Safety
TDOT TDOT PIN: 124165.03
Davidson County Total Cost: $24,640,000.00
I-24 and Bell Rd (SR-254) (Exit 59) Total Programmed: $1,840,000.00
ramps at I-24 and Bell Rd (SR-254) (Exit 59) Federal Share: $1,656,000.00
0.30 miles Federal Obligation*: $756,000.00
Exempt Unobligated Balance: $900,000.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2021PE-NNHPP$840,000.00$756,000.00$84,000.00$0.00
2021PE-DNHPP$1,000,000.00$900,000.00$100,000.00$0.00
TOTAL  $1,840,000.00$1,656,000.00$184,000.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
2/8/2021PE-NNHPP$756,000.00AUTHORIZE
TOTAL  $756,000.00 

Project Images and Videos

2020-14-103_Image

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2020-015This amendment adds the project to the TIP with $960,000 federal NHPP funds in FY 2021 allocated by TDOT.6/17/2020  

Administrative Modifications

Adjustment #ActionMPO Approval
2021-013This project has been modified to add $696,000 (federal) NHPP funds and to modify the funding split from 80 federal/20 state to 90 federal/10 state.12/18/2020

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.