TIP Project #2002-028: Rockland Road Widening & Extension

This project will realign Rockland Road to connect to Center Point Road and widen existing Rockland Road from 2 to 3 lanes from West Main Street to Imperial Boulevard. The project will include drainage, curb and gutter, a multi-use path or sidewalk and landscaping.

M Road Widening Regional Plan ID: 2678
Hendersonville TDOT PIN: 043162.00
Sumner County Total Cost: $14,850,000.00
Rockland Rd Total Programmed: $933,500.00
Center Point Rd to Imperial Blvd Federal Share: $746,800.00
2.40 miles Federal Obligation*:
Non-Exempt Unobligated Balance: $746,800.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2020PE-D, PE-NU-STBG$200,000.00$160,000.00$0.00$40,000.00
2021ROWU-STBG$733,500.00$586,800.00$0.00$146,700.00
TOTAL  $933,500.00$746,800.00$0.00$186,700.00

Construction Reserve Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2022CONSTRUCTIONU-RSV$3,750,000.00$3,000,000.00$0.00$750,000.00
TOTAL  $3,750,000.00$3,000,000.00$0.00$750,000.00

Obligated Funds

There is no obligated funding information for this TIP Project.

Project Images and Videos

2002-028

Project Documents and Links

Project Notes

NotePosted On
The City of Hendersonville plans to begin NEPA/PE in fiscal year 2020. Extension letter was sent to TDOT requesting additional time to begin project. Local matching dollars will be programmed in the City’s next budget cycle. Any changes to the project scope and budget will be submitted at the time the project begins with TDOT.5/14/2019

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2021-030This amendment revises the project name from “Rockland Road Widening” to “Rockland Road Widening & Extension.” The project description will be revised to include a realignment/extension of Rockland Road from its current terminus just east of the interchange on West Main Street (SR-6/US31E) to Center Point Road to the west. The new termini for the project will be Center Point Road to Imperial Boulevard.9/15/2021  

Administrative Modifications

There are no administrative modifications for this TIP Project.

Submit a Comment