TIP Project #2016-84-231: SR-99 (US-412) Interchange Modification

Modification of the I-65 interchange at SR-99 (US-412).

M Interchange Regional Plan ID: 1624-109
TDOT TDOT PIN: 115786.00
Maury County Total Cost: $45,640,000.00
SR-99 (US-412) Total Programmed: $37,000,000.00
I-65 at SR-99 (US-412) Federal Share: $4,197,308.00
1.10 miles Federal Obligation*: $4,769,185.30
Non-Exempt Unobligated Balance: ($571,877.30)
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2021CONSTRUCTIONNHPP (AC)$32,802,692.00$0.00$32,802,692.00$0.00
2023CONSTRUCTIONU-CRRSAA$4,197,308.00$4,197,308.00$0.00$0.00
TOTAL  $37,000,000.00$4,197,308.00$32,802,692.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
1/31/2020PE-NNHPP$460,800.00ADJUST
9/14/2020PE-NNHPP$27,900.00ADJUST
8/24/2021PE-NIM$83,177.30ADJUST
6/2/2023CONSTRUCTIONU-CRRSAA$4,197,308.00ADJUST
TOTAL  $4,769,185.30 

Project Images and Videos

2016-84-231 Location Map

Project Documents and Links

Project Notes

There are no notes for this TIP Project.

Project Amendments

There are no amendments for this TIP Project.

Administrative Modifications

Adjustment #ActionMPO Approval
2021-008This project has been modified to add $1,300,000 state funds to the project and to convert all funding to state funds (intended advance construction for NHPP).12/17/2020
2023-027This project has been modified to replace $4,197,308 NHPP(AC) funds with the same amount of U-CRRSAA funds in FY 2023.6/02/2023

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*  
Phone #:  
Email address:  

Your comment:

Please limit your comment to 2,000 characters.