| 2023-001 | This project has been amended to add $693,618 additional federal TAP dollars awarded to the project by TDOT’s Transportation Alternatives Program. | 3/15/2023 | 6/29/2023 | 7/03/2023 |
| 2023-018 | This amendment adds $796,084 additional federal TAP dollars awarded to the project by TDOT’s Transportation Alternatives Program. | 7/19/2023 | 8/25/2023 | 8/30/2023 |
| 2026-009 | Project is split into phase I (2022-76-158) and phase II (2026-76-188) projects. $1,898,662.00 (Federal) is shifted to phase II, including $128,592 in L-STBG funds, $1,710,070 in TAP funds, and $60,000 in Federal L-STBG funds for design. | 2/04/2026 | | |