TIP Project #2023-89-117: National Highway Performance Program (NHPP) Grouping

Projects for the preservation and improvement of the conditions and performance of the National Highway System (NHS), including: Rehabilitation, resurfacing, restoration, preservation, and operational improvements; Traffic operations; Bridge and tunnel improvements; Safety improvements; Bicycle and pedestrian improvements; and Environmental mitigation. Please refer to Appendix G of the TIP document for more information about and work allowable from this grouping.

M Road Upgrades Regional Plan ID: Preservation
TDOT TDOT PIN: 126756.00
Multi-County Total Cost: $316,294,200.00
National Highway Performance Program (NHPP) Grouping Total Programmed: $316,294,200.00
Regionwide - Nashville Area MPO Federal Share: $200,235,360.00
0.00 miles Federal Obligation*: $130,820,577.00
Exempt Unobligated Balance: $69,414,783.00
* Obligations during current TIP period only.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2023PE-N, PE-D, ROW, CONSTRUCTIONNHPP$74,425,600.00$59,540,480.00$14,885,120.00$0.00
2024PE-N, PE-D, ROW, CONSTRUCTIONNHPP$69,315,600.00$55,452,480.00$13,863,120.00$0.00
2025PE-N, PE-D, ROW, CONSTRUCTIONNHPP$51,553,000.00$41,242,400.00$10,310,600.00$0.00
2026PE-N, PE-D, ROW, CONSTRUCTIONNHPP$55,000,000.00$44,000,000.00$11,000,000.00$0.00
2026PE-N, PE-D, ROW, CONSTRUCTIONNHPP (AC)$66,000,000.00$0.00$66,000,000.00$0.00
TOTAL  $316,294,200.00$200,235,360.00$116,058,840.00$0.00

Construction Reserve Funds

There is no reserve funding information for this TIP Project.

Obligated Funds

Obligation DatePhaseFunding SourceFederal FundsNotes
11/6/2023CONSTRUCTIONNHPP$1,721,376.00AUTHORIZE
11/6/2023CONSTRUCTIONNHPP$3,990,879.00AUTHORIZE
11/9/2023PE-NNHPP$21,600.00ADJUST
1/3/2024CONSTRUCTIONNHPP$1,413,632.00AUTHORIZE
1/3/2024CONSTRUCTIONNHPP$2,505,264.00AUTHORIZE
1/3/2024CONSTRUCTIONNHPP$1,868,360.00AUTHORIZE
1/3/2024CONSTRUCTIONNHPP$7,897,581.00AUTHORIZE
1/3/2024CONSTRUCTIONNHPP$4,276,962.00AUTHORIZE
1/29/2024PE-D; ROWNHPP$647,147.00ADJUST; AUTHORIZE
1/31/2024CONSTRUCTIONNHPP$785,851.00ADJUST
2/14/2024CONSTRUCTIONNHPP$2,075,776.00AUTHORIZE
2/14/2024CONSTRUCTIONNHPP$983,792.00AUTHORIZE
2/14/2024CONSTRUCTIONNHPP$760,776.00AUTHORIZE
2/14/2024CONSTRUCTIONNHPP$7,537,428.00AUTHORIZE
2/14/2024CONSTRUCTIONNHPP$4,663,305.00AUTHORIZE
4/3/2024PROJECTNHPP$5,262,400.00AUTHORIZE
4/3/2024PROJECTNHPP$2,100,686.00AUTHORIZE
4/3/2024PROJECTNHPP$316,800.00AUTHORIZE
5/2/2024CONSTRUCTIONNHPP$801,538.00ADJUST
5/31/2024CONSTRUCTIONNHPP$1,572,244.00CONVERT AC
5/31/2024CONSTRUCTIONNHPP$21,219.00ADJUST
5/31/2024CONSTRUCTIONNHPP$1,319,468.00ADJUST
8/30/2024CONSTRUCTIONSTBG-U$3,976,173.00AUTHORIZE
8/30/2024CONSTRUCTIONSTBG-U$4,580,784.00AUTHORIZE
8/30/2024CONSTRUCTIONSTBG-U$5,254,227.00AUTHORIZE
9/3/2024PE-N; CONSTRUCTIONNHPP$608,384.00ADJUST; AUTHORIZE
9/19/2024CONSTRUCTIONSTBG-U$1,966,772.00CONVERT AC
11/4/2024CONSTRUCTIONNHPP$3,278,817.00AUTHORIZE
11/4/2024CONSTRUCTIONNHPP$3,856,752.00AUTHORIZE
11/4/2024CONSTRUCTIONNHPP$5,021,568.00AUTHORIZE
11/7/2024CONSTRUCTIONNHPP$328,502.00ADJUST
12/18/2024CONSTRUCTIONNHPP$527,099.00ADJUST
12/23/2024CONSTRUCTIONNHPP$1,156,272.00AUTHORIZE
2/10/2025CONSTRUCTIONNHPP$1,647,616.00AUTHORIZE
2/10/2025CONSTRUCTIONNHPP$7,159,644.00AUTHORIZE
2/10/2025CONSTRUCTIONNHPP$8,094,861.00AUTHORIZE
2/10/2025CONSTRUCTIONNHPP$10,866,096.00AUTHORIZE
2/21/2025PE-NNHPP$48,000.00AUTHORIZE
3/21/2025CONSTRUCTIONNHPP$4,073,032.00AUTHORIZE
3/21/2025CONSTRUCTIONNHPP$5,328,208.00AUTHORIZE
5/7/2025CONSTRUCTIONNHPP$58,465.00ADJUST
5/27/2025PE-D; CONSTRUCTIONNHPP$444,000.00ADJUST
6/6/2025IMPLEMENTATIONNHPP$348,480.00ADJUST
6/6/2025IMPLEMENTATIONNHPP$2,430,755.00ADJUST
6/6/2025IMPLEMENTATIONNHPP$5,788,640.00ADJUST
6/12/2025PE-NNHPP$80,000.00AUTHORIZE
7/23/2025PE-N; PE-DNHPP$1,353,346.00ADJUST
TOTAL  $130,820,577.00 

Project Images and Videos

 There are no images for this TIP Project.

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

There are no amendments for this TIP Project.

Administrative Modifications

Adjustment #ActionMPO Approval
2024-012This project has been modified to add $480,000 in federal NHPP funds to the FY 2024 PE-N/PE-D/ROW/CONST phase and update the total project cost.1/18/2024
2026-003This modification adds $66,000,000 of State funds to FY 26 for future Advanced Construction funds to be converted.10/27/2025
2026-006Mod 753: TDOT is adding $9,899,600 to FY 2026 NHPP at 80/20 federal/state to fund projects in upcoming lettings. Total Project Cost is increased to $311,294,200.3/10/2026
2026-009TDOT is adding $5,000,000 to FY 2026 NHPP at 80/20 federal/state to fund projects in the upcoming letting. Total Project Cost is increased to $316,294,200. 4/15/2026

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.