TIP Project #2011-41-144: Cherry Lane Extension with I-840 Interchange

Proposed Amendment (revision)

Construct new 5 lane facility needed to provide alternative access to and relieve congestion on NW Broad (US-41/70) and Thompson Lane (SR-268)

M New Road Regional Plan ID: 2717
Murfreesboro TDOT PIN: 116200.00
Rutherford County Total Cost: $51,892,000.00
Cherry Lane Extension with I-840 Interchange Total Programmed: $19,033,168.50
From Sulphur Springs Road to NW Broad Street and interchange @ I-840 Federal Share: $15,226,534.80
2.60 miles Federal Obligation*:
Non-Exempt Unobligated Balance: $15,226,534.80
*obligations to date during current TIP period
View the approved version.

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2025ROWM-STBG$2,312,500.00$1,850,000.00$0.00$462,500.00
2025CONSTRUCTIONM-STBG$16,470,668.50$13,176,534.80$0.00$3,294,133.70
2025PE-DM-STBG$250,000.00$200,000.00$0.00$50,000.00
TOTAL  $19,033,168.50$15,226,534.80$0.00$3,806,633.70

Construction Reserve Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2025CONSTRUCTIONM-RSV$112,363.75$89,891.00$0.00$22,472.75
TOTAL  $112,363.75$89,891.00$0.00$22,472.75

Obligated Funds

There is no obligated funding information for this TIP Project.

Project Images and Videos

2011-41-144_Image

Project Notes

NotePosted On
This amendment proposes to remove the FY 2025 Local funding line and add 1,229,056 of Federal M-STBG funds to FY 2025 PE-D, ROW, and Construction.3/07/2025

Submit a Comment for this Draft

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.

   


Proposed Amendment (revision)