Proposed Amendment (revision)
This project involves the construction of sidewalks along North Main Street (SR-243) from Hay Long Avenue to Park Avenue. Project also includes ADA upgrades, signage, retaining wall, landscaping, pedestrian lighting and pedestrian amenities.
|
Type:
|
M Multi-Modal Upgrades
|
Regional Plan ID:
|
Multimodal
|
Lead Agency
|
Mt. Pleasant
|
TDOT PIN:
|
126660.00
|
County
|
Maury County
|
Total Cost:
|
$6,950,060.00
|
Name/Route:
|
N Main St (SR-243)
|
Total Programmed:
|
$6,733,316.50
|
Location:
|
Hay Long Ave to Park Ave
|
Federal Share:
|
$4,367,161.00
|
Length:
|
0.10 miles
|
Federal Obligation*:
|
$1,298,517.00
|
Air Quality Status:
|
Exempt
|
Unobligated Balance:
|
$3,068,644.00
|
|
|
<< BACK
|
Project in
Transportation Improvement Program for FYs 2023-2026
|
|
|
Programmed Funds
2023 | CONSTRUCTION | L-STBG | $60,647.50 | $48,518.00 | $0.00 | $12,129.50 |
2023 | CONSTRUCTION | TAP | $1,562,500.00 | $1,250,000.00 | $0.00 | $312,500.00 |
2025 | CONSTRUCTION | LOCAL | $1,274,365.00 | $0.00 | $0.00 | $1,274,365.00 |
2025 | CONSTRUCTION | TAP | $3,318,719.00 | $2,654,975.00 | $0.00 | $663,744.00 |
2025 | CONSTRUCTION | U-TAP | $517,085.00 | $413,668.00 | $0.00 | $103,417.00 |
TOTAL | | | $6,733,316.50 | $4,367,161.00 | $0.00 | $2,366,155.50 |
Construction Reserve Funds
There is no reserve funding information for this TIP Project.
|
Obligated Funds
3/22/2023 | CONSTRUCTION | L-STBG (Mt. Pleasant) | $48,518.00 | AUTHORIZE |
3/22/2023 | CONSTRUCTION | TAP | $1,249,999.00 | AUTHORIZE |
TOTAL | | | $1,298,517.00 | |
Project Images and Videos
Project Documents and Links
There are no documents or links for this TIP Project. |
Project Notes
This amendment shifts $413,668 of FY 25 federal U-TAP funds from TIP#2023-86-8888 to replace previously locally funded TAP eligible construction activities. | 7/07/2025 |
Proposed Amendment (revision)