12/17/12 - Schedule:
Oct 2014 - New/amended contract with TDOT.
Nov 2014 - Receive Notice To Proceed from TDOT for PE.
Dec 2014-Sept 2015 - PE NEPA and Design.
Oct 2015 - Notice To Proceed from TDOT for ROW and Utilities.
Nov 2015-Sept 2016 - Acquire ROW; adjust utilities.
Oct 2016-Sept 2017 - Construction and closeout.
The project will be managed by the City’s Public Works Department and Engineering Consultant. All contracts (engineering, ROW acquisition and construction) will include schedules with milestones and dates. One of the main criteria in choosing the engineering consultant will be performance and proven knowledge of TDOT requirements and track record in working with TDOT
| 12/17/2012 |