TIP Project #2008-56-082: Lower Station Camp Creek Road Streetscape and Pavement Project (Greenway) Phase 1

Convert a portion of the roadway to non-motorized transportation use. The project will be a combination of new alignment and existing roadway. It begins at Big Station camp Blvd. and extends to Lower Station Camp Creek Road. Phase 1 will extend from Stone Creek Subdivision trail head to Bison Trail trail head.

Sumner County   M Greenway
Sumner County   1056-299
Lower Station Camp Creek Road Streetscape and Pavement Project (Greenway)   110618.00; 110618.01; 110618.02
Big Station Camp Blvd from Stone Creek Subdivision trail head to Bison Trail trail head.  
0.80 miles   $944,250.00
Exempt   $874,400.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2014PE-DU-STP$17,000.00$13,600.00$0.00$3,400.00
2014ROWU-STP$54,000.00$43,200.00$0.00$10,800.00
2016CONSTRUCTIONU-ALT$803,400.00$642,720.00$0.00$160,680.00
TOTAL  $874,400.00$699,520.00$0.00$174,880.00

Project Image Gallery

Lower Station Camp Creek Greenway

Lower Station Camp Creek Greenway

Lower Station Camp Creek Greenway

Lower Station Camp Creek Greenway

Lower Station Camp Creek Greenway

Project Notes

NotePosted On
12/18/12 - Phase 1: Design Completed in 2010. Currently in Right of Way Stage - updated appraisal and review appraisal completed in April 2011, negotiations began with property owner in May 2011. Negotiation with property owner continues. Construction funding for Phase 1 is included in this TIP request. The construction of the Phase 1 greenway trail is anticipated to last 150 days. Phase 2: Design Completed in 2011. Right of Way Stage Complete and approved by TDOT Advertised for Bids in August 2011 - Notice to Proceed to Contractor for Construction in December 2011. Construction completion in July 2012 Phase 2 Grand Opening Event held in October 2012. Phase 3: Phase 3A Engineering Design Completion December 2011. Submittal of Design Plans to funding agency January 2012. Active Transportation Grant Announcement January 2012. Advertised for Bids in October 2012 - Notice of Award given to Contractor in November 2012. Construction Completion is anticipated to be May 2013. Phase 3B Phase 3B Engineering Design will begin in January 2013 with design completion in April 2013. Construction funding for Phase 3B is included in this TIP request. The construction of the Phase 3B greenway trail and pedestrian bridge is anticipated to last 180 days. The County will utilize Wiser Company for the Phase 3B design. Wiser Company has completed all of the design for the Lower Station Camp Greenway phases. Phase 3B design should be completed in April 2013. The TIP funding will be utilized for construction and construction engineering inspection fees. Once design is complete in April and construction funds are obtained, Phase 3B will be ready to proceed to construction. Phase 1 design has been completed; Phase 1 will be ready to proceed to construction once the right of way is obtained. The Lower Station Camp Greenway is a priority project for Sumner County.12/18/2012

Project Amendments

There are no amendments for this TIP Project.

List of Administrative Modifications

Adjustment #ActionMPO Approval
2016-031This project is being adjusted to change the funding type for CONST from U-RSV to U-ALT. This change is made possible by a removal of U-ALT funds from TIP# 2015-66-066.8/15/2016

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.