TIP Project #2015-17-217: Berry Hill ITS Traffic Signal Coordination Project

This project will provide funds to expand the fiber backbone within the city limits of Berry Hill to its twelve (12) signalized intersections and upgrade traffic signals at each intersection.

Metro Nashville   M ITS
Davidson County  
various intersections in the Berry Hill city limits  
various intersections in the Berry Hill city limits  
0.00 miles   $1,845,000.00
Exempt   $1,845,000.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2016PE-D, CONSTRUCTION, PE-NCMAQ$118,000.00$118,000.00$0.00$0.00
2017PE-D, CONSTRUCTIONCMAQ$1,727,000.00$1,727,000.00$0.00$0.00
TOTAL  $1,845,000.00$1,845,000.00$0.00$0.00

Project Image Gallery

 There are no images for this TIP Project.

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2015-042Berry Hill (sponsored by Metro Nashville) was awarded funding for this project by the TDOT Long Range Planning Division following the 2015 Congestion Mitigation and Air Quality Improvement (CMAQ) Program’s competitive call for projects. This amendment adds the newly funded project to the TIP under the CMAQ allowance in the MPO’s 2035 Regional Transportation Plan.9/16/2015  

List of Administrative Modifications

Adjustment #ActionMPO Approval
2016-039This project is being adjusted to add PE-N as an eligible type of work in FY16. There is no change to project funding.9/02/2016

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.