TIP Project #2014-75-021: Hamilton Springs Station Construction

Construction of a permanent multimodal commuter rail station along the existing Music City Star Rail Line.

RTA   M Transit Capital
Wilson County   Consistent
Hamilton Springs Station Construction  
Music City Star Line @ Hamilton Springs  
0.00 miles   $2,000,000.00
Exempt   $2,000,000.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2014PE-D, PE-NU-STP$160,000.00$128,000.00$0.00$32,000.00
2015CONSTRUCTIONU-STP$1,840,000.00$1,472,000.00$0.00$368,000.00
TOTAL  $2,000,000.00$1,600,000.00$0.00$400,000.00

Project Image Gallery

2014-75-021

Hamilton Springs Station - Proposed Project Delivery Timeline

Project Documents and Links

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2015-020This project is being amended to commit $1,472,000 (federal) in U-STP funds held in the MPO’s construction reserve for this project. Preliminary engineering and design is underway, with completion of those phases anticipated in spring of 2015.3/18/2015  

List of Administrative Modifications

There are no administrative modifications for this TIP Project.

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.