TIP Project #2006-014: New Shackle Island Road (SR-258) - Phase 1

Widen New Shackle Island Road from SR-386 to Iris Drive from 3 lanes to 5. Bike/ped facilities included.

Hendersonville   M Road Widening
Sumner County   1052-176
New Shackle Island Road (SR-258) - Phase 1  
Iris Drive north to SR-386 (Vietnam Veterans Blvd)  
0.80 miles   $4,964,644.00
Non-Exempt   $3,975,030.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2011ROW, UTILITIESU-STP$555,530.00$444,424.00$0.00$111,106.00
2012ROW, UTILITIESU-STP$175,000.00$140,000.00$0.00$35,000.00
2012CONSTRUCTIONU-STP$3,244,500.00$2,595,600.00$0.00$648,900.00
TOTAL  $3,975,030.00$3,180,024.00$0.00$795,006.00

Project Image Gallery

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2012-043Unutilized Preliminary Engineering funds shifted to Right-of-Way/Utilities phase and programmed in FY 2012. U-STP funds programmed from the reserve for Construction in accordance with Programming Policy # 9 of the FY 2011-15 TIP.6/20/20127/06/20127/24/2012

List of Administrative Modifications

There are no administrative modifications for this TIP Project.

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.