2011-002 | Add previous phase (PE) and shift $112,000 (federal) in U-STP funds from ROW to PE to finalize design changes associated with ROW acquisition completion | 4/25/2011 |
2013-027 | Project modified to shift $75,000 (federal share) from CONST to PE for design modifications during construction and PE phase close-out. The total project cost remained the same. | 5/21/2013 |