2011-017 | Project adjusted to subdivide the PE phase to include PE-NEPA by shifting $1,353,600 (federal) from PE-Design. Additionally, $240,000 (federal) from PE are being shifted to TIP project # 2011-42-142 - Thompson Lane Widening to supplement funding for ROW in FY 2013. | 6/30/2011 |