Transportation Improvement Program for FYs 2020-2023

#Reload the page Map

Program Summary

Draft TIP for Fiscal Years 2020 through 2023

$1,040,492,186.44 163
$624,462,237.35 9/21/2016
0 10/1/2016 through 9/30/2020
0 No amendments.
* Obligations during current TIP period only. Anna Emerson (615) 862-7157, emerson@nashvillempo.org

Project List

Search for projects by keyword:    

162 projects meet the search criteria:

TIP ID#Project NameImprovementLocationLead AgencyTotal Cost
2002-028Rockland Road WideningMRoad WideningSumner CountyHendersonville$12,624,690.00
2002-029Walton Ferry and Old Shackle Island Rd Improvements ProjectMIntersectionSumner CountyHendersonville$12,565,325.00
2004-005Jefferson Street IntersectionsMIntersectionDavidson CountyMetro Nashville$3,870,000.00
2005-0065307 Urban Operating for Rover Public Transit - Relax & Ride ServiceMTransit OperationsRutherford CountyMurfreesboro Public Transit$600,000.00
2005-0075307 Urban Operating for Rover Public Transit - Mid-Cumberland Human Resource Agency (MCHRA) ContractMTransit OperationsRutherford CountyMurfreesboro Public Transit$910,000.00
2008-14-030Various intersection improvements (FAUB routes)MIntersectionDavidson CountyMetro Nashville$8,593,750.00
2008-15-048Transit Miscellaneous Capital SupportMTransit CapitalDavidson CountyNashville MTA$4,863,910.00
2008-15-049MTA - Administration Building Rehabilitation (Nestor)MTransit CapitalDavidson CountyNashville MTA$3,506,450.00
2008-15-052Paratransit Buses Purchase and ReplacementMTransit CapitalDavidson CountyNashville MTA$11,135,866.00
2008-15-054Bus Purchase and ReplacementMTransit CapitalDavidson CountyNashville MTA$62,982,809.00
Show # of items:

List of Proposed Amendments

No proposed amendments available

Reports & Tables

Report Name Description
bullet Custom Project List Report Print or export a detailed list of all or selected projects
bullet Project Information Sheets Print or export detailed information about individual projects
bullet Funding Summary by Program Year and Grant Source View current balances of programmed funds by year and grant
Request another type of report Send us your request

Related Documents and Links

There are no files or links found for this TIP.

List of Amendments

There are no amendments for projects in this TIP.

List of Administrative Modifications

Adjustment #TIP ID#ProjectActionMPO Approval
2020-0012008-15-052Paratransit Buses Purchase and ReplacementThis project has been adjusted to remove $2,500,000 LOCAL funds in FY 2020 and replace with $3,008,692 (federal) FTA 5339 funds apportioned to the Nashville MTA in FY 17 and FY 18. 2/18/2020
2020-0022012-47-173Smyrna Signal SystemThis project has been adjusted to update the total project cost to $993,024.2/26/2020
2020-0032018-46-080Florence Road SidewalksThis project has been adjusted to add "PE" as an eligible phase of work.2/27/2020
2020-0042017-66-045SR-96 West Multi-Use Trail - Phases 1 & 2This project has been modified to add $472,992 in LOCAL funds for construction.4/06/2020
2020-0052016-18-234Old Shiloh Road Bridge over Mansker CreekThis project has been modified to add $96,000 (federal) for PE-N, remove programmed ROW funds, and add $169,460 (federal) BRR-L funds in FY 2020. State and local matches have also been modified.4/09/2020
2020-0062019-63-088Buckner Road Extension from Buckner Lane to Lewisburg Pike (SR-106/US431) with a New Interchange at I-65This project has been modified to show BUILD grant funds at a 100% federal share (removing local matching funds) and to add $2,928,097 (federal) NHPP funds in FY 2020.4/15/2020
2020-0072014-111-027Complete Streets Implementation on BRT Lite Corridors - Murfreesboro PikeThis project has been modified to update the total project cost to be inclusive of previous phases of work.4/16/2020
2020-0082015-57-216Gallatin ITS & Signal Coordination ProjectThis project has been modified to add PE as an eligible type of work in FY 2020 and to shift $177,250 (federal) CMAQ funds from the CONST phase of work to the ITS phase in order to cover all costs associated with software purchasing. Additionally, $175,000 (federal) that was obligated under the previous TIP has been removed from the amount of currently programmed CMAQ funds.4/17/2020
2020-0092017-62-038Murfreesboro Pike (SR-96) Widening (Segment 1)This project has been added to the TIP via administrative modification per FHWA consult and approval based upon "the recency of the termination of the FY 2017-2020 STIP/TIP and the impacts of the MPO’s meeting schedule [during the COVID-19 pandemic] on this project’s development, among other considerations." It was TDOT's intention that this project be included in the FY20-23 TIP during initial TIP development.4/22/2020
2020-0102018-76-078Highway 231 North Sidewalk ProjectThis project has been modified to revise the total project cost to match an estimated cost for construction.4/27/2020


Name the search:
OR

For example: "roadways 2016", "MPO construction projects"

Replace an existing search:

Updates the selected search with the current search criteria.

InfoYour saved searches are available on the My View tab.