TIP Project #2011-42-143: Bradyville Pike (SR-99) Widening

Widen from 2 to 3 lanes with sidewalks, bike lanes and transit shelters.

Murfreesboro   M Road Widening
Rutherford County   1042-131
Bradyville Pike (SR-99) Widening  
From US-41 (SE Broad St.) to Rutherford Blvd  
2.10 miles   $7,378,400.00
Non-Exempt   $2,380,000.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2012PE-NM-STP$880,000.00$704,000.00$0.00$176,000.00
2012PE-DM-STP$220,000.00$176,000.00$0.00$44,000.00
2012ROWM-STP$734,400.00$587,520.00$0.00$146,880.00
2012ROWSTP$545,600.00$436,480.00$109,120.00$0.00
TOTAL  $2,380,000.00$1,904,000.00$109,120.00$366,880.00

Project Image Gallery

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2012-070The amendment adds $436,480 (federal share) for Right-of-Way from State Surface Transportation Program (STP) funds to match the negotiated amounts in the contract with TDOT.9/19/201210/23/201211/19/2012

List of Administrative Modifications

Adjustment #ActionMPO Approval
2012-004The project was modified to subdivide the PE phase to include PE-NEPA in FY2012 by shifting $88,704 (federal) from PE-Design. Also, the fiscal year for PE-D was changed to 2012.1/10/2012
2012-025Project modified to shift Murfreesboro Urbanized Area STP funds between project phases to match the negotiated amounts in the contract with TDOT. The total amount of programmed funds for the project remained the same.7/19/2012

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.