TIP Project #2011-610-165: Fairview 3R Improvement Projects Grouping

Resurfacing, restoration and rehabilitation improvements of various roads in the City of Fairview

Fairview   M Resurfacing
Williamson County   Consistent
 
Various roads within the City of Fairview  
0.00 miles   $642,770.00
Exempt   $607,643.00
<<BACK

Programmed Funds

Fiscal YearPhaseFunding SourceTotal FundsFederal FundsState FundsLocal Funds
2013PE-NL-STP$24,000.00$19,200.00$0.00$4,800.00
2013PE-DL-STP$21,000.00$16,800.00$0.00$4,200.00
2013CONSTRUCTIONL-STP$562,643.00$450,114.00$0.00$112,529.00
TOTAL  $607,643.00$486,114.00$0.00$121,529.00

Project Image Gallery

2011-610-165_Fairview 3R Improvements

Project Documents and Links

There are no documents or links for this TIP Project.

Project Notes

There are no notes for this TIP Project.

Project Amendments

Amendment #ActionMPO ApprovalTDOT ApprovalUS DOT Approval
2011-026Project added to the TIP9/21/20119/27/201110/11/2011
2013-022The amendment adds $301,600 (federal share) in Local STP funds to FY 2013 for Construction phase. The additional funds added to this project are being shifted from Fairview’s TIP project #2012-61-175 – City Center Way Extension.3/20/20135/15/20135/22/2013

List of Administrative Modifications

Adjustment #ActionMPO Approval
2012-015Project modified to shift $3,200 (federal) from PE-D to PE-N in FY 2012. The total project cost remained the same.5/04/2012

Submit a Comment

The Nashville Metropolitan Planning Organization welcomes your feedback. Please enter your comment below and click Submit. While we review all comments carefully, we are not able to respond to every comment.

Your name:*
Phone #:
Email address:

Your comment:

Please limit your comment to 2,000 characters.