Transportation Improvement Program for FYs 2023-2026

#Reload the page Map

Program Summary

TIP for Fiscal Years 2023 through 2026

$2,079,983,676.57 226
$1,340,548,358.85 11/16/2022
$218,439,981.52 10/1/2022 through 9/30/2026
$1,122,108,377.33 No amendments.
* Obligations during current TIP period only. Shea Northfield at 615-862-8854, tip@gnrc.org

Project List

Search for projects by keyword:    

220 projects meet the search criteria:

TIP ID#Project NameImprovementLocationLead AgencyTotal Cost
2002-029Walton Ferry and Old Shackle Island Rd Improvements ProjectMIntersectionSumner CountyHendersonville$35,573,574.06
2004-005Jefferson Street IntersectionsMIntersectionDavidson CountyMetro Nashville$5,621,000.00
2005-0065307 Urban Operating for Rover Public Transit - Relax & Ride ServiceMTransit OperationsRutherford CountyMurfreesboro Public Transit$370,000.00
2005-0075307 Urban Operating for Rover Public Transit - Mid-Cumberland Human Resource Agency (MCHRA) ContractMTransit OperationsRutherford CountyMurfreesboro Public Transit$3,000,000.00
2008-14-030Various intersection improvements (FAUB routes)MIntersectionDavidson CountyMetro Nashville$12,053,750.00
2008-15-048Transit Miscellaneous Capital SupportMTransit CapitalDavidson CountyNashville MTA$24,276,630.00
2008-15-049MTA - Administration Building Rehabilitation (Nestor)MTransit CapitalDavidson CountyNashville MTA$8,250,000.00
2008-15-052Paratransit Buses Purchase and ReplacementMTransit CapitalDavidson CountyNashville MTA$17,628,846.00
2008-15-054Bus Purchase and ReplacementMTransit CapitalDavidson CountyNashville MTA$69,499,400.00
2008-45-0895307 Urban Operating for Rover Public Transit - Fixed Route ServiceMTransit OperationsRutherford CountyMurfreesboro Public Transit$6,650,000.00
Show # of items:

List of Proposed Amendments

No proposed amendments available

Reports & Tables

Report Name Description
bullet Custom Project List Report Print or export a detailed list of all or selected projects
bullet Project Information Sheets Print or export detailed information about individual projects
bullet Funding Summary by Program Year and Grant Source View current balances of programmed funds by year and grant
Request another type of report Send us your request

Related Documents and Links

There are no files or links found for this TIP.

List of Amendments

Amendment #TIP ID#ProjectActionMPO AdoptionTDOTFederal
2023-0012022-76-158Cedar City Pedestrian ImprovementsThis project has been amended to add $693,618 additional federal TAP dollars awarded to the project by TDOT’s Transportation Alternatives Program.3/15/20236/29/20237/03/2023
2023-0022022-72-164Hartsville Pike (SR-141) Widening, From North of Lovers Lane to SR-26 (US-70)This amendment adds $10,800,000 federal STBG dollars provided to the project by TDOT.3/15/20236/29/20237/03/2023
2023-0032008-64-037SR-106 (Hillsboro Rd) and SR-46 Re-alignment/ Signalization.This amendment adds $800,000 federal U-HIP funds provided to the project by GNRC and to program $382,119 federal U-STBG funds previously held in construction reserve.3/15/20236/29/20237/03/2023
2023-0042023-411-167Eagleville Downtown Revitalization Segments 1 & 2This amendment adds the project to the TIP with $1,078,992 state funds awarded by TDOT’s Multimodal Access Grant program.3/15/20236/29/20237/03/2023
2023-0052023-26-168North Main Street Sidewalk Phase 1This amendment adds the project to the TIP with $1,125,000 state funds awarded by TDOT’s Multimodal Access Grant program.3/15/20236/29/20237/03/2023
2023-0062023-56-169Vol State-Gap Trail - Phase 2BThis amendment adds the project to the TIP with $954,603 federal TAP funds provided by TDOT’s Transportation Alternatives program.5/17/20238/25/20238/30/2023
2023-0072023-211-170Mt. Pleasant Downtown Revitalization – Phase 2This amendment adds the project to the TIP with $1,854,975 federal TAP funds provided by TDOT’s Transportation Alternatives program.5/17/20238/25/20238/30/2023
2023-0082020-66-098Thompsons Station Multimodal Connectivity - Phase 3This amendment adds $1,322,253 federal TAP funds provided by TDOT’s Transportation Alternatives Program to the project for construction in FY 2023. Previously awarded TAP funds for construction were also moved to FY 2023.5/17/20238/25/20238/30/2023
2023-0092014-85-023RTA Miscellaneous Transit Capital Support & Passenger AmenitiesThis amendment adds $491,040 FTA 5307 funds shifted from TIP# 2008-85-091 and $2,318,563 FTA 5337 funds shifted from TIP# 2019-85-126 to the project for implementation in FY 2023.5/17/20237/17/20237/31/2023
2023-0102015-111-069North Nashville Transit CenterThis amendment adds $4,922,240 federal FTA 5307 funds to the project for construction and implementation across all fiscal years.5/17/20237/17/20237/31/2023

List of Administrative Modifications

Adjustment #TIP ID#ProjectActionMPO Approval
2023-0012023-89-099Highway Infrastructure Program (Grouping)This project has been modified to shift $800,000 federal U-HIP to TIP# 2008-64-037.6/28/2023
2023-0022022-72-164Hartsville Pike (SR-141) Widening, From North of Lovers Lane to SR-26 (US-70)This project has been modified to add $2,500,000 federal STBG funds for the FY 2023 construction phase.7/10/2023
2023-0032014-45-0205307 Urban Capital for Rover Public Transit- New Transit FacilityThis project has been modified to add $3,000,000 in STATE IMPROVE Act funds for the FY 2025 construction phase. 7/11/2023
2023-0042008-15-052Paratransit Buses Purchase and ReplacementThis project has been modified to add $2,958,703 in federal FTA 5339 funds for the FY 2023 implementation phase.7/12/2023
2023-0052008-15-048Transit Miscellaneous Capital SupportThis project has been modified to add $2,852,160 in federal FTA 5307 funds for the FY 2023 implementation phase. The project description has also been modified. 7/12/2023
2023-0062023-85-147Job Access and Reverse Commute Program (Grouping)This project has been modified to add $120,000 in federal FTA 5307 funds for the FY 2023 implementation phase.7/12/2023
2023-0072015-65-060Bus & Bus FacilitiesThis project has been modified to add $100,000 in federal FTA 5307 funds for the FY 2023 implementation phase.7/12/2023
2023-0082018-65-056Bus Operating Assistance - Franklin Transit AuthorityThis project has been modified to add $195,461 in federal FTA 5307 funds for the FY 2023 implementation phase and $20,000 in federal FTA 5307 funds for the FY 2024 implementation phase. 7/12/2023
2023-0092019-65-128Vanpool Operating AssistanceThis project has been modified to add $140,748 in federal FTA 5307 funds for the FY 2023 implementation phase. 7/12/2023
2023-0102022-77-153Mt. Juliet Road (SR-171) ITS & Signal Improvements Project – Phase 3This project has been modified to shift $50,000 in federal CMAQ funds from the FY 2023 ROW phase to the FY 2023 PE-D phase. $25,729 in LOCAL funds was also added for the FY 2023 PE-D phase. There was also a fund transfer of $62,226.72 CMAQ funds from previously obligated FY 2023 PE-N phase to the FY 2023 PE-D phase. 7/13/2023


Name the search:
OR

For example: "roadways 2016", "MPO construction projects"

Replace an existing search:

Updates the selected search with the current search criteria.

InfoYour saved searches are available on the My View tab.